Sunday, June 10, 2012

Day 4 - a litte more concrete

So we aggreed to widen the initial slab of 3m x 9m with an extra 1m x 4m section. This meant that this morning was taken up with digging out a new level and forming up the extra bit we needed to pour. In addition to the additional bit of floor space we concreted around the existing bathroom to allow room for the panels to be secured and have space next to the shower for changing etc. This took a significant amount of time as the whole existing bathroom structure needed to be demolished and the fence moved so we could get round the back of it. Once the concrete was down we needed to reconstruct a bathroom type structure to allow them to use the bathroom.

No comments: